The capital costs for the initial Streetcar system are estimated to be $64.3 million. The route extensions would add $31.5 million for a total combined cost of $95.8 million.
The annual operating cost is estimated at $2.62 million for the initial Streetcar route and $3.85 million for the initial route and route extensions.
Capital and Operating Cost Summary
| |
Initial Route |
Initial Route & Route Extensions |
| Construction |
$34.2 million |
$53.9 million |
| Vehicles / Vehicle Cost |
5 vehicles / $15.8 million |
6 vehicles / $18.9 million |
| Project Management / Contingency |
$14.3 million |
$23.0 million |
| Total Capital |
$64.3 million |
$95.8 million |
| Federal Government |
$54.9 million |
$79.9 million |
| Local Share |
$9.7 million |
$16.2 million |
| Annual Operating Cost |
$2.62 million |
$3.85 million |
|