Streetcar Capital and Operating Costs
Streetcar Governance
Streetcar Finance
Potential Future Streetcar Extensions
Streetcar Next Steps

The capital costs for the initial Streetcar system are estimated to be $64.3 million. The route extensions would add $31.5 million for a total combined cost of $95.8 million.

The annual operating cost is estimated at $2.62 million for the initial Streetcar route and $3.85 million for the initial route and route extensions.

Capital and Operating Cost Summary

  Initial Route Initial Route & Route Extensions
Construction $34.2 million $53.9 million
Vehicles / Vehicle Cost 5 vehicles / $15.8 million 6 vehicles / $18.9 million
Project Management / Contingency $14.3 million $23.0 million
Total Capital $64.3 million $95.8 million
Federal Government $54.9 million $79.9 million
Local Share $9.7 million $16.2 million
Annual Operating Cost $2.62 million $3.85 million